Mullen Road
The Mullen Road Improvement is structured to unfold in several phases, each carefully designed to minimize disruptions and ensure the safety of residents and commuters.
The initial phase involves the closure of Mullen Road from Silver Maple to Cambridge, a step scheduled to take place 5-8 weeks from the project's initiation, contingent on administrative timelines.
Following this, the focus will shift to the intersection of Cambridge & Mullen, slated for closure in mid-June or later, paving the way for the construction of a much-anticipated roundabout.
As the project progresses, the city pledges to keep the community well-informed, with detailed traffic control plans and detours shared in advance of each major phase. This transparent approach aims to facilitate smooth navigation for residents and businesses alike.
The comprehensive scope of the project includes resurfacing Mullen from Route 58 to Silver Maple Drive. Additionally, Mullen's transformation involves a substantial reconstruction and widening effort, expanding the road to five lanes. This configuration includes two lanes in each direction, separated by a median, with occasional turn lanes strategically placed near intersections. This project will install a roundabout at the Mullen/Cambridge intersection, a measure aimed at enhancing traffic flow and ensuring safety.
Belton residents can look forward to a nicer, more efficient Mullen Road, reflecting the city's commitment to progress and improved infrastructure. Stay tuned for updates and detailed traffic plans.
Status:Complete
Estimated Completion: Late 2024
Project Map(PDF, 3MB)
Update Week of May 19, 2025
Striping is complete and the project achieved substantial completion.
Update Week of May 5, 2025
Most of the lane lines were completed and the contractor is expected to complete remaining work next week.
Update Week of April 21, 2025
Asphalt repair work and striping prep work is being done to be started next week.
Update Week of April 14, 2025
Arrows and yield lines were installed last week. Asphalt repair work is scheduled soon, along with the long pavement marking lines. Various punch list work is ongoing and is nearing completion.
Update Week of April 7, 2025
Striping work has started on Mullen, along with punch list work and will continue into next week.
Update Week of March 10, 2025
Striping and signing work is estimated to start the last week of March or first week of April, weather dependent.
Update Week of Sept. 30, 2024
Storm sewer and water main work were completed at the intersection of Mullen & Cambridge. UPDATE 9/4/2024: Starting Thursday, September 5, Mullen Road will reopen up to Sycamore, but please note that the right lane in each direction will be closed for sidewalk work. Mullen will remain closed from Sycamore to Cambridge. The link below provides an overview of the planned traffic and lane closures. Further information regarding the Mullen/Cambridge intersection will be provided in the coming days. Click here for more information.
Update Week of Aug. 26, 2024
Curb and median curb installations have been completed. Paving is scheduled for 8/27 or 8/28, and Mullen Road north of Cambridge is tentatively expected to reopen around 8/30 or early the following week.
Update Week of Aug. 19, 2024
Curb installation was halted due to poor weather conditions and the curb crew rescheduled for Tuesday, 8/20. Paving is tentatively planned for later this week, pending any further weather delays.
Update Week of July 29, 2024
Curb installation is planned to begin Tuesday, 8/6/2024. Due to the heat the contractor decided to push the concrete pour back.
Update Week of July 8, 2024
The contractor has completed all underground work between Silver Maple Dr and Cambridge Rd. The area has been graded to subgrade and is currently being allowed to dry to ensure it will pass a proof roll. Once this drying process is complete, the contractor will proceed with cement-treating the subgrade and constructing the road.
Update Week of May 13, 2024
As of last week, Mullen Road is closed from Silver Maple Drive to Cambridge Road. The contractor has removed all existing pavement in this area and is nearing completion of the storm sewer, which is anticipated to be finished this week. The water main work along Mullen between Silver Maple and Cambridge is also complete. Next steps include rough grading and preparing for the cement treated base (CTB). Once the CTB is in place, curb installation will begin, followed by paving. After the paving is completed, we will move into Stage 2: Mullen Road will reopen to Sycamore, and the Cambridge Road intersection will close. At that point, Traditions will regain access at Sycamore.
Update Week of March 18, 2024
The contractor has made significant progress by installing the majority of the water main and is currently undergoing testing procedures. However, commencement of the storm sewer work is pending until all precast components arrive. In the meantime, they have been utilizing available time to carry out rough grading across the project site.