Cherry Hill Stormwater Improvements

  • Project typeStormwater Improvement
  • Project value$140,000
  • Project scheduleFall 2020 - Spring 2021
  • Contractor namePyramid Construction, LLC
Cherry Hill Culvert

Project Description/Information

An existing 54" corrugated metal pipe carrying stormwater from an inlet on Cherry Hill Drive to a water-quality detention pond was in a failed condition and causing ground settlement and sinkholes. This project included installing a cure-in-place liner in the pipe, repairing the headwall, and installing riprap at the pipe outlet reducing the potential for erosion and improving water quality. 

Funding

This project was funded with General Obligation (GO) Bonds that were approved by voters in April 2019.

Location

Cherry Hill Drive,  64012  View Map

Google Map